Province | Subbasin | % |
---|---|---|
Columbia Plateau | Yakima | 100.00% |
Previous: | Next: |
---|---|
56662 REL 218: 1997-013-25 EXP YKFP (LOWER YAKIMA) SUPPLEMENTATION COMPLEX O&M |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | A: 119. Project implementation management and contract administration | 06/30/2022 | 06/28/2022 | |
Compliance documentation and assistance for environmental and cultural resource clearances | B: 165. Environmental and Cultural Resource compliance assistance and clearance documentation | 06/30/2022 | 06/28/2022 | |
Safe and effective operation and maintenance of YKFP (lower) sites and facilities | C: 61. Operate & Maintain the Prosser Hatchery, Marion Drain Hatchery and the Acclimation Sites | 06/30/2022 | 06/28/2022 | |
Maintain fish health of LYRSR project fish | D: 60. USFWS to Maintain Fish Health: Lower Yakima River Supplementation and Research Facilities | 06/30/2022 | 06/28/2022 | |
Reintroduce Coho to the Yakima Basin | E: 176. Reintroduction of Coho in the Yakima Basin (BY 2020): Phase II (rear-acclimate-release) | 06/30/2022 | 06/28/2022 | |
Reintroduce coho to the Yakima Basin | F: 176. Reintroduction of Coho in the Yakima Basin (BY 2021): Phase I (collect-spawn-incubate-rear) | 06/30/2022 | 06/28/2022 | |
Increase Yakima River Mainstem Fall Chinook through supplementation | G: 176. Supplementation to Increase Yakima Mainstem Subyearling Fall Chinook (BY 2021) | 06/30/2022 | 06/28/2022 | |
Produce Early Fall/Summer Chinook (BY21) | H: 176. Produce Early Fall/Summer Chinook: sub-yearlings (BY 2021) | 06/30/2022 | 06/28/2022 | |
Updated Annual Plans | I: 174. Update (2021): a) Annual Operation Plan; and b) Annual Maintenance Plan | 02/28/2022 | 02/28/2022 | |
Produce monthly reports (Quarterly) | J: 141. Other Reports for BPA | 06/30/2022 | 06/28/2022 | |
Submit Progress Report (2-year) for: Jan 2020 to Dec 2021 | M: 132. Progress Report (2-year): Calendar-year 2020 and 2021 (01/01/2020 - 12/31/2021) | 06/30/2022 | 06/28/2022 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU |
|
Coho (O. kisutch) - Unspecified Population |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Project implementation management and contract administration | |||||||
B | 165 | Environmental and Cultural Resource compliance assistance and clearance documentation | |||||||
C | 61 | Operate & Maintain the Prosser Hatchery, Marion Drain Hatchery and the Acclimation Sites | 04/27/2021 | ||||||
D | 60 | USFWS to Maintain Fish Health: Lower Yakima River Supplementation and Research Facilities | 04/27/2021 | ||||||
E | 176 | Reintroduction of Coho in the Yakima Basin (BY 2020): Phase II (rear-acclimate-release) | 04/27/2021 | ||||||
F | 176 | Reintroduction of Coho in the Yakima Basin (BY 2021): Phase I (collect-spawn-incubate-rear) | 04/27/2021 | ||||||
G | 176 | Supplementation to Increase Yakima Mainstem Subyearling Fall Chinook (BY 2021) | 04/27/2021 | ||||||
H | 176 | Produce Early Fall/Summer Chinook: sub-yearlings (BY 2021) | 04/27/2021 | ||||||
I | 174 | Update (2021): a) Annual Operation Plan; and b) Annual Maintenance Plan | 04/27/2021 | ||||||
J | 141 | Other Reports for BPA | |||||||
K | 171 | Overhead Cover (Marion Drain): Replace failing overhead screening with structural roof to protect and maintain circular rearing tanks | |||||||
L | 185 | Periodic Status Reports for BPA | |||||||
M | 132 | Progress Report (2-year): Calendar-year 2020 and 2021 (01/01/2020 - 12/31/2021) |